Acceptance Testing
Agree the scenarios, tools, and test data needed to validate your complete integration in Staging before go-live.
1. Introduction
Acceptance testing confirms that your connectivity, consumer consent flow, and Ozone Connect implementation work together as expected before go-live.
The test scenarios are tailored to your products, digital channels, consumer types, and agreed implementation scope. They also check that the CDR APIs provide the data available to the same consumers through your digital channels.
Use the outcome of your mapping exercise to define the scope. Agree the scenarios and success criteria with your Ozone delivery team before testing starts.
2. Integration checklist
| Action | Guidance | Task |
|---|---|---|
| 1 | Acceptance test scenarios | Agree the test scope, scenarios, tools, data, environments, and success criteria with your Ozone delivery team |
3. Requirements
The following sections explain the areas typically tested, the tools available, and the test data needed.
3.1 Acceptance test scenarios
Each scenario should identify what is being tested, how the test will be performed, and the expected result.
The agreed scenarios typically cover the following areas.
| Area | What to validate |
|---|---|
| Connectivity | TLS and mTLS connections in each direction, using the certificates agreed during Connectivity Setup |
| Consent journey | Redirects, screens, and API calls across your supported digital channels, including successful journeys and declined, cancelled, failed, or timed-out journeys |
| Consumer dashboard | Viewing and withdrawing sharing arrangements, including notification of the withdrawal to the ADR, and amendments to existing arrangements |
| Ozone Connect | Every endpoint in scope returns the expected data or service outcome, with the correct success and error responses |
| Product parity | The API data and services match those available to the same consumers through your digital channels, across the account and consumer types in scope |
| Performance, availability, and reporting | Response times and stability under expected ADR traffic, availability, and the CDR metrics and outage reporting |
3.1.1 Tools
Agree which tools to use and how their results will support acceptance testing.
| Tool | Purpose |
|---|---|
| CDR Conformance Test Suite (CTS) | The ACCC's conformance testing, run by your organisation through the CDR Participant Portal before go-live. See CDR Conformance Test Suite |
| Postman collections | Test individual API calls manually and explore request and response behaviour. Download the CDR collection from the Resources menu in the Admin Portal |
| Stress and performance testing tools | Validate response times and stability under expected and peak ADR traffic |
| Admin Portal logs | Trace calls through the integration, including API and Ozone Connect activity linked by Interaction ID |
3.1.2 Test data and environments
Run acceptance testing in Staging, using your actual Ozone Connect implementation and consumer consent application.
Prepare test consumers and accounts that represent the products and scenarios in scope. Depending on your offering, these may include:
- Personal and business consumers.
- Single and joint accounts, including the joint account settings in scope.
- Different account types.
The test data should allow you to verify both successful outcomes and the agreed error paths.
3.1.3 CDR Conformance Test Suite (CTS)
Before your organisation can be made active on the CDR Register and receive the production certificate, you must pass the ACCC's Conformance Test Suite. Your organisation runs CTS through the CDR Participant Portal, against an Ozone test environment. Ozone does not run the tests, but your Ozone delivery team prepares the environment and supports you during the run.
All CTS scenarios must pass in a single run. If one scenario fails, the full suite must be run again.
Before you start
| Prerequisite | What it involves |
|---|---|
| CTS test certificate | Ozone generates the CSR. You submit it through the Participant Portal and return the issued test certificate to Ozone. See Certificates |
| Network access | Allow incoming calls from the CTS IP address listed in the ACCC's CTS Connection Datasheet for Data Holders |
| Conformance ID | Share the CTS Conformance ID you receive at enrolment with your Ozone delivery team. It is used in the CTS Register URLs |
| CTS Register | Ozone temporarily points the test environment to the CTS Register, and shortens the Register polling interval so the scenarios do not wait for the normal polling cycle |
| Discovery document | Confirm that the .well-known endpoint lists the correct URLs and supported configuration |
What CTS covers
CTS tests your conformance to the Consumer Data Standards by simulating the CDR Register and an ADR. The scenarios include:
- OpenID Connect discovery and mTLS checks on the information security endpoints, including rejected client certificates.
- Dynamic Client Registration: creating, updating and retrieving a registration.
- First and second consents for the same consumer, holder-of-key resource requests, and consent amendment.
- Arrangement revocation by the ADR and by the data holder, and token revocation.
- Rejection of badly formed client assertions.
- A software product whose status changes to
REMOVED.
CTS does not test every endpoint. It does not check the data returned by the banking APIs, the Get Metrics response, internal consent handling, or compliance with the joint account, secondary user and nominated representative rules. Cover these in your acceptance test scenarios. Check the ACCC's current CTS guidance for the scenarios that apply to your CDS version.
Additional scenarios to include
Consider adding these scenarios, which are common in production but not covered by CTS:
- A one-off consent, where
sharing_durationis0or not provided. - A consent that requests only customer data, with no accounts.
- A consent authorised with no accounts selected.
- A business account consent authorised by a nominated representative.
- Userinfo requests with and without the
profilescope. - An ADR software product changing from active to inactive, and back to active.
- Invalid authorisation requests, such as a request sent directly to the authorisation endpoint without PAR, or a PAR request without the
openidscope.
Action 1: Agree acceptance test scenariosAgree the following with your Ozone delivery team before testing:
- The areas, products, consumer types, and digital channels in scope.
- The scenarios and expected outcomes.
- The tools to use.
- The test data and Staging environments needed.
- The criteria for a successful result.
Updated 7 days ago